Assist with scheduling inspections, tracking issues, and coordinating with contractors.
Started Nov 15, 2024, 8:00 AM
Good morning team. Setting up this group to coordinate on the Riverside Tower project inspections.
Thanks Mike. I have the foundation inspection scheduled for next Tuesday.
We should have the rebar work completed by Monday afternoon.
I will be doing the electrical rough-in inspection. Please ensure all junction boxes are accessible.
Noted Elena. David, can you make sure the crew clears access paths?
Will do. What time works best for the inspection?
Thursday at 10 AM would be ideal for me.
Heads up - I found some concerns with the soil compaction report. We may need additional testing.
Can you share the specific areas of concern?
Northwest corner near the property line. Readings were below spec at 85% instead of required 95%.
We can re-compact that section. Should add about 2 days to the foundation timeline.
Better to do it right. Schedule the re-work and let me know when ready for re-inspection.
Re-compaction complete. New readings all above 96%.
Great. I can come by tomorrow morning to verify.
Soil inspection passed. You are clear to proceed with foundation pour.
Excellent news. Concrete trucks scheduled for Wednesday 6 AM.
Reminder: I still need the updated electrical plans before my inspection.
David, can you get those to Elena today?
Just emailed them over. Rev 3 with the panel relocations.
Got them. Thanks David. See everyone Thursday.